Which state has the most data centers?
Virginia has the most data centers in the U.S., with 398 operating and 287 more planned as of February 2026, according to Pew Research Center's analysis of Data Center Map. Texas is second with 296 operating and 170 planned, followed by California (277 operating), Ohio (166) and New York (148). The Build-Out Gap in Figure 1 ranks the 15 states with the most data centers by their combined total and draws each state's pipeline as the blue bar between what it runs today and what it will run once every planned site opens.
How many data centers are in the U.S.?
The U.S. has more than 3,000 operating data centers and more than 1,500 in development, Pew found. Pew counts a data center as planned if it is listed as under construction, planned or land banked, and it drops projects marked canceled or uncertain. The four Census regions add up to 1,556 planned sites. Other trackers count differently, so state totals vary by source.
Where are new data centers being built?
Most new data centers are going to the South and Midwest, which together hold three-quarters of the U.S. pipeline. The South alone has 754 planned sites, 48% of the total. Georgia's 141 planned data centers would add 150% to its 94 operating ones, the largest jump of any top-15 state, and Indiana's pipeline (54) is also bigger than its base (38). Two-thirds (67%) of planned data centers are in rural areas, against 13% of those operating today, and 39% are in counties that have none yet.
The biggest sites point the same way. Synergy Research Group, which tracks 21 major cloud and internet companies, says Texas and the Midwest held 33% of operating U.S. hyperscale capacity at the end of 2025 but account for 53% of the capacity in its pipeline. It calls Texas "by a wide margin" the most prominent state in that pipeline, and names Wisconsin, Indiana, Michigan and Missouri as fast risers in the Midwest. The U.S. had 580 operating hyperscale data centers at the end of 2025 and 437 more in Synergy's pipeline.
How much electricity do data centers use by state?
Data centers used 25.59% of Virginia's electricity in 2023, about 33.85 terawatt-hours, according to EPRI estimates. That is more than six times the national share, which EPRI puts at about 4%. Five other states passed 10%: North Dakota (15.42%), Nebraska (11.70%), Iowa (11.43%), Oregon (11.39%) and Wyoming (11.26%). Texas has the second-largest data center load (21.81 TWh) but a much bigger grid, so data centers made up only 4.59% of its use. EPRI found that 15 states accounted for about 80% of national data center load.
Will Texas pass Virginia in data centers?
It depends on the tracker. In Pew's Data Center Map figures, Virginia leads Texas on both operating sites (398 vs. 296) and planned ones (287 vs. 170). Aterio, the data provider behind Visual Capitalist's ranking, counts differently: it projects Texas reaching 962 total sites across operating, under-construction and announced projects, ahead of Virginia's 954. Synergy says Northern Virginia will keep the single biggest concentration of hyperscale data centers, even as new capacity shifts toward Texas.
Methodology & caveats
There is no official count of U.S. data centers. Figures 1, 4, 5 and 6 and three of the stat tiles use Pew Research Center's analysis of Data Center Map, an industry database, as of February 19, 2026. Pew published the top 15 states only. A planned data center is one listed as under construction, planned or land banked; planned sites can be delayed or canceled, and a single campus may count as several data centers. Figure 4 (planned as a share of operating) and the 1,556 regional total were calculated by dev.co from Pew's counts.
Electricity figures (Figures 2 and 3) are EPRI estimates for 2023 from its May 2024 Powering Intelligence report, so they predate the 2025–2026 pipeline in the other cards. EPRI lists 44 states with significant data center load; the other six are left blank in Figure 2. Figure 3 converts EPRI's MWh per year to TWh. Synergy's shares measure hyperscale IT capacity for 21 large operators, not facility counts. Aterio's Texas and Virginia figures are cited via a reprint of Visual Capitalist's article because Aterio's own site could not be reached; they use a different database and definitions from Pew's, so the two sets of counts should not be mixed.
Sources
- [1]Pew Research Center. Most new data centers in the U.S. are coming to rural areas (Apr 13, 2026), analysis of Data Center Map data accessed Feb. 19, 2026https://www.pewresearch.org/short-reads/2026/04/13/most-new-data-centers-in-the-us-are-coming-to-rural-areas/
- [2]Aterio (via Visual Capitalist). Where the servers reside: Texas and Virginia lead data center boom (Visual Capitalist, reprinted in Real Assets Adviser, June 2026)https://irei.com/publications/article/where-the-servers-reside-texas-and-virginia-lead-data-center-boom/
- [3]Synergy Research Group. U.S. Hyperscale Investment Shifts Decisively Inland (Apr 13, 2026)https://www.srgresearch.com/articles/focus-of-us-hyperscale-investment-shifts-dramatically-inland
- [4]Electric Power Research Institute. Powering Intelligence: Analyzing Artificial Intelligence and Data Center Energy Consumption (May 2024): Table 2 and Table A1, 2023 data center load by statehttps://restservice.epri.com/publicdownload/000000003002028905/0/Product