Data Centers by State: Operating and Planned (2026)

Virginia runs 398 data centers and has 287 more in the pipeline, but the next wave is heading inland and to rural counties. The Build-Out Gap sets each state's pipeline against what it runs today.

Fig. 1

The Build-Out Gap

States with the most data centers, Feb. 2026. The ring is what each state operates today; the solid dot adds every data center under construction, planned or land banked. The blue bar between them is the pipeline.

Operating Operating + planned Gap (Operating + planned − Operating)
0100200300400500600700GapVirginia398685+287Texas296466+170California277331+54Illinois139262+123Georgia94235+141Ohio166223+57Arizona98184+86New York148154+6Oregon115142+27Washington124135+11Pennsylvania78129+51Florida120128+8North Carolina72113+41Iowa64105+41Indiana3892+54

Top 15 states by total, as published by Pew Research Center from Data Center Map. Planned includes projects listed as under construction, planned or land banked; canceled and uncertain projects are excluded. Counts depend on the database: Aterio's tracker, which counts differently, puts Virginia at 320 operating sites and projects Texas (962 total sites) to pass Virginia (954).

Operating data centers in Virginia
398
Most of any state; Texas is next with 296
New U.S. data centers in development
1,500+
On top of more than 3,000 operating today
Planned data centers in rural areas
67%
vs. 13% of those operating today
Texas & Midwest share of new hyperscale capacity
53%
Up from 33% of operating capacity at end-2025
Fig. 2

Data centers use a quarter of Virginia's electricity

Data center electricity use by state, 2023, as a share of each state's total. Each square fills to that share on a 0–30% scale; the dashed line is the U.S. average of about 4%.

Fill: 0.00% (empty) to 30.00% (full) U.S. ≈4%
VA25.59%VA25.59%ND15.42%ND15.42%NE11.70%NE11.70%IA11.43%IA11.43%OR11.39%OR11.39%WY11.26%WY11.26%NV8.69%NV8.69%UT7.68%UT7.68%AZ7.43%AZ7.43%WA5.69%WA5.69%IL5.48%IL5.48%NJ5.42%NJ5.42%TX4.59%TX4.59%GA4.26%GA4.26%MT3.71%MT3.71%CA3.70%CA3.70%PA3.16%PA3.16%NY2.84%NY2.84%CO2.66%CO2.66%SC2.45%SC2.45%KY2.15%KY2.15%MA2.08%MA2.08%NC1.92%NC1.92%OK1.76%OK1.76%AL1.71%AL1.71%OH1.58%OH1.58%NM1.48%NM1.48%TN1.30%TN1.30%MN1.24%MN1.24%MO1.21%MO1.21%CT0.95%CT0.95%ID0.57%ID0.57%FL0.56%FL0.56%MI0.52%MI0.52%SD0.52%SD0.52%RI0.23%RI0.23%ME0.22%ME0.22%WI0.21%WI0.21%IN0.19%IN0.19%MD0.16%MD0.16%NH0.16%NH0.16%HI0.10%HI0.10%LA0.08%LA0.08%KS0.02%KS0.02%

EPRI estimates. Table A1 covers the 44 states with significant data center load in 2023; Alaska, Arkansas, Delaware, Mississippi, Vermont and West Virginia are not listed and are left blank. The U.S. figure is EPRI's "about 4%" average estimate.

Fig. 3

Virginia's data centers use more power than any other state's

Data center electricity use by state, top 15, 2023, terawatt-hours

Virginia33.85 TWhTexas21.81 TWhCalifornia9.33 TWhIllinois7.45 TWhOregon6.41 TWhArizona6.25 TWhIowa6.19 TWhGeorgia6.18 TWhWashington5.17 TWhPennsylvania4.59 TWhNew York4.07 TWhNew Jersey4.04 TWhNebraska3.96 TWhNorth Dakota3.92 TWhNevada3.42 TWh

EPRI estimates, converted by dev.co from MWh per year (33,851,122 MWh = 33.85 TWh). EPRI says these 15 states made up about 80% of national data center load in 2023.

Fig. 4

Georgia's pipeline is bigger than what it runs today

Planned data centers by state as a share of operating ones, Feb. 2026, top 15 states

Georgia150%Indiana142%Illinois88%Arizona88%Virginia72%Pennsylvania65%Iowa64%Texas57%North Carolina57%Ohio34%Oregon23%California19%Washington9%Florida7%New York4%

Calculated by dev.co: planned ÷ operating, from Pew's counts. Georgia has 141 planned vs. 94 operating; Indiana 54 vs. 38. New York (6 planned vs. 148 operating) has the smallest pipeline relative to its base.

Fig. 5

Nearly half of planned data centers are in the South

Planned data centers by U.S. Census region, Feb. 2026

48.5%26.9%17.8%
  • South75448.5%
  • Midwest41926.9%
  • West27717.8%
  • Northeast1066.8%
  • All planned1,556100%

The total is the sum of Pew's four regional counts (Pew rounds it to "more than 1,500"). The South includes Virginia, Texas and Georgia. Planned counts would raise each region's existing total by 62% (South), 64% (Midwest), 34% (West) and 26% (Northeast).

Fig. 6

Two-thirds of the next wave is going rural

Share of U.S. data centers in rural vs. urban areas, by status, Feb. 2026

RuralUrban
0%25%50%75%100%PlannedRural 67%Urban 33%Operating13%Urban 87%

Urban and rural follow U.S. Census Bureau definitions. Pew also found that 39% of planned data centers are in counties that have none today.